The JKUAT Student Centre To Get A Ksh 5 Million Face Lift

128
(Last Updated On: February 21, 2018)
Want create site? Find Free WordPress Themes and plugins.

On the 19th date of February, 2018, the Jomo Kenyatta University Students Association (JKUSA) commissioned a facelift of the Students Centre at the University Main Campus. In the groundbreaking ceremony officially presided over by the Vice Chancellor Prof. Mabel Imbuga accompanied by other senior members of the University management, the ambitious plan of revamping the Students Centre was set in motion. Speaking at the event held at the Center, the Vice Chancellor lauded the JKUSA officials for spearheading the initiative, and implored on the contractor to stick to the contract timelines and deliver quality.

“This is the first project of such a magnitude to be done by students, for the students and it’s a move in the right direction. Also worth noting is the fact that the contractor working on this is a former student of ours, Mr. Dennis Mumo, who studied Construction Management” she opined.

The refurbishment of the Students Centre is set to cost Kshs. 5.7 million, and will entail its reconstruction into an ultra-modern state of the art facility. Some notable features of the new Centre include new offices for religious groups within the University, a state of the art fully equipped gym, a lounge, increased interior and exterior sitting spaces, gaming areas, TV rooms, among others. The visionary initiative is a brainchild of the students’ government, and the funding comes from the resources allocated to the running of the Students’ Association.

Vice Chancellor Prof. Mabel Imbuga is taken through the blueprint of the new Centre

Speaking at the groundbreaking ceremony, the JKUSA Finance Secretary Mr. Ibrahim Boru asserted that the current sorry state of the Centre leaves nothing to write home about, considering the significant role the student centre plays, not just to students but also to staff and parents when they visit the University.

“This is why we’re determined to see this facelift to its completion, and this project is not for JKUSA, it’s for all comrades. I can guarantee to all skeptics that it will go through, and we are ready to be judged based on that,” he added.

Comrades keenly following proceedings at the groundbreaking ceremony.

The project will be done in two phases, with the first phase expected to be complete in 16 weeks.This will entail refurbishment of the Kitchen, Eating Area, and the Lounge. Students have been advised to keep off the facility once construction begins. The Deputy Vice Chancellor in charge of Finance, Prof. Benard Moirongo, himself a professional architect, assured students and management of his commitment to working closely with the contractors and seeing to the success of the project.

This change is quite an exciting improvement to JKUAT and the students are ready to avoid the long journey to Thika to party but will now have a place in their campus.

Courtesy of jkuat.ac.ke.

Did you find apk for android? You can find new Free Android Games and apps.
JOIN OUR NEWSLETTER
Join over 3.000 visitors who are receiving our newsletter and staying in the know on our top articles, latest events and upcoming activities!Click here and join the community today.
We hate spam. Your email address will not be sold or shared with anyone else.